The PLC has been converted into the Summer Church.
All new kneelers have been built, stained and covered.
All the old kneelers have been removed.
Removal of the pews and kneelers began on May 12th
Old green carpet was removed
Plastic dust containment is now in place
Baptismal Font has been removed
Old tile in front of the pews has been removed
Flooring/tiles have been ordered
Wooden risers are installed
Existing tile was cleaned, buffed and polished.
Field tile has been delivered.
Most of the painting has been completed in the Sanctuary
Risers were added to the Altar steps
Field tile was installed
All tile has been grouted
Carpet has been installed
Pews and kneelers have been installed
Baptismal Font has shipped from Italy
Font has arrived and been installed
Church work is completed
What is next?
In the next few months, we will replace the carpet in the Bride's Room, Work Sacristy, Priest Sacristy and Usher's Room. These were not part of the Capital Campaign, but needed projects that will come out of our plant maintenance budget.
We saved the kneeler for the beautiful oak wood...soon to be tables, stands, folding screens and cutting boards from our Holy Oak Wordshop/photoalbums/sanctuary-remodel/thumbnail_Kneel%202.jpg_parent